UPDATE 12
February 2017
Back to News Page

1 February 2017
A bumper crop of pictures for this update! The new roof is on and will have all the slates on by the end of the week. We have finalised the mechanical and electrical layout and the first fix is underway as you can see by the cables hanging down in many of the photos below. You can also see the new upstairs room which will will give us so much more space! There is still the odd feature that you will recognsie from the original building is the photos below but most things have changed beyond recognition! The "round window" above the schoolroom door for example is now the rectangular window shown the the third picture!